Spanish Fork Santaquin Pipeline - Santaquin Reach




Project Overview

Central Utah Water Conservancy District (CUWCD) is installing approximately 23,048 feet of 60-inch diameter steel pipe within Santaquin City and Utah County to deliver water for municipal and industrial use. Additionally, water delivery turnouts will be constructed along an existing 60-inch pipeline within Mapleton, Salem, and Payson. This is the last reach of the Spanish Fork Santaquin Pipeline and marks the completion of this system which will have the capacity to deliver 23,090 acre-feet of water each year to South Utah County.

Construction on this project will be done by VanCon, Inc. and is scheduled to begin March 2024. Construction is estimated to be completed May 2026.

Regular construction updates will be posted on this website. Questions and concerns can be directed to the project hotline at 877-458-2463 or santaquinreach@gmail.com.

Santaquin Reach

Spanish Fork Santaquin Pipeline - Santaquin Reach

Spanish Fork Santaquin Pipeline

Spanish Fork Santaquin Pipeline